Green Cabinets is a custom cabinet builder. They recently completed a set of kitchen cabinets (Job Number 1478), as summarized below:
Green Cabinets is a custom cabinet builder. They recently completed a set of kitchen cabinets (Job Number 1478), as summarized below. Job Number: 1478 Date Started: 4/07/20×5 Date Completed: 4/22/20×5 Description: Cherry kitchen cabinets Applied Direct Materials Direct Labor Manufacturing Overhead Req. No Amount Ticket Hours Amount Hours Rate Amount 385 $ 365 128 $ 456 391 275 130 710 396 165 133 252 401 270 Total $1,075 Total 57S 1418 Cost Summary Direct Material Cost $1,075 Direct Labor Cost 1,418 Applied Manufacturing Overhead Total Cost Green Cabinets applies overhead to jobs at a rate of $10 per direct labor hour. (a) How much overhead would be applied to Job Number 1478? Applied Manufacturing Overhead